By Lindley Lund
USD 475
USD 475 Board of Education members have approved a request to approve the Guaranteed Maximum Price (GMP) Package #2 for the new Fort Riley elementary school. In December, the Board approved the early release of GMP Package #1 for $3,995,987. During the bid opening on Jan. 5, the competitive bid pricing was secured for GMP Package #2 from Hutton Construction at $7,616,417. This package includes site grading (rough and final), underground storm, water, gas and electrical utilities, and paving (including curbs and gutters).
The Board approved this amendment, allowing for the purchase of long lead time utility supplies and timely preparation of the site for the start of the vertical construction when spring weather permits.