USD 475 released photos received from the contractors on the new Junction City High School construction.The blue FRC panels have started to go up.Paint, Ceiling grid, wall tile, and cabinetry crews are working their way west of area E into the SET academy. (picture take from SET commons, looking towards English and sp ed classrooms)Football fieldMore curtain walls have been installed in zone 1! Below is looking into the commons between the FSA and SET academies.They are hard to see, but both stairs in the FSA wing (area A) have been installed and glazers are installing the curtain wall.Construction is on target for completion by Aug. 2021.