Jan 16, 2021

New Junction City High School construction continues on schedule

Posted Jan 16, 2021 6:00 PM

The new Junction City High School is scheduled to be open and serving students by the beginning of the 2021-2022 school year. USD 475 Chief Operations Officer David Wild confirmed this past week that the construction remains on schedule.

Wild said finishes are starting for the academic areas referred to as Zone 1. This includes flooring, carpeting in corridors, mill work and ceiling grids in the Business academy area with a target completion date of March 1st. Fire system testing will occur in late January.

Finish crews will continue working from east to west through the Science and Freshman academies. Shop areas on the north side of the facility will be heated next week. Finish work in those areas will then get underway. Target completion for these areas is May 1st.

Front office, Media Center and Fine Arts roofing and fire proofing is being completed. Installation of electrical service will finalize by mid-February. Placing of wall board and primer coats is underway in protected areas. Auditorium stage rigging and motor installation is underway with all overhead work to be completed by the end of January.

Football visitor concrete work is done. The visitor bleachers at Simpler stadium will removed and installed at the new site starting next week. Final turf has been put down and the initial layer of the running track surface has been placed.

The Junction City High School carpentry class continues to work on framing up the visitor’s football ticket booth. Structural steel for the baseball / softball concessions is being finalized. Roofing and brick placement will start in early February.

Lighting for the football field went up this past week. Perimeter fencing and sidewalk installation is ongoing. 

Project completion remains on schedule for June of 2021 with an August opening for the fall 2021 semester.