KDOT will begin the Traffic Signalization for the K-18/Karns Roundabout Project starting on February 1st.
According to Junction City Public Works Director Ray Ibarra, traffic on K-18 will be down to one lane signalized traffic between Munson Rd and Spring Valley Rd. There will be no access onto Karns Drive to the Middle School from K-18.
Traffic to the Middle School will be only on Wildcat Lane. During hours of 7:00 to 8:00 a.m. and 2:45 to 3:15 p.m. on Wildcat Lane there will only be “Right Hand Turn Only” traffic during the stated hours.
The work involved will be constructing a roundabout on K-18 that will serve the Middle School and the New High School with the projected time for completion for June 2022.