Junction City Commissioners have approved the 2022 Street Maintenance Program for $1,734,142.40.
Public Works Director Ray Ibarra reported that Bayers has started the 2022 Street Maintenance Project. They have completed all the mill and overlay on the Greenhill’s streets and Cedar St.: Rebud Dr., Hawthorne Circle, Hawthorne Dr., Goldenrod Circle, Columbine Dr., Mistletoe Circle., Woodlawn Cir., Cedar St. and Highland Circle
Bayers has completed the mill and overlay on Elmdale Ave. from 18th to 21st St., Custer Rd from Westwood Blvd. to 20th St, 18th St. from Bel Air to Custer Rd. and Jefferson St. from 18th to 11th St